F & G and T & I Joint Committee

Wednesday, March 31, 2021 · 9:00 AM AM · 26th Floor, Council Chambers

TL;DR

The F & G and T & I Joint Committee met to discuss a major water infrastructure project in the west side of the city. The committee considered a $1.9 million contract with Pyramid Excavation & Construction to replace water mains in several neighborhoods, including areas near West City Limits and Wornall Road.

Key Decisions

  • Water Main Replacement Contract Held in Committee

Agenda

  1. PUBLIC OBSERVANCE OF MEETINGS Members of the City Council may attend this meeting via videoconference. Any closed session may be held via teleconference. The public can observe this meeting at the links provided below. Applicants and citizens wishing to participate have the option of attending each meeting or they may do so through the videoconference platform ZOOM, using this link: https://us02web.zoom.us/j/84530222968
  2. 210278 Authorizing a $1,881,352.00 construction contract with Pyramid Excavation & Construction, Inc., for the replacement of water mains in the area of West City Limits to Wornall Road, W. 85th Street to W. 93rd Street, and at the Stone Henge Townhomes at 1-143 W. Bannister Road; and authorizing a maximum expenditure of $2,075,000.00.
    Ordinance
  3. HELD IN COMMITTEE
  4. ADDITIONAL BUSINESS