South Platte River Committee

Wednesday, August 19, 2026 · 1:30 PM AM · City & County Building, Council Committee Room, Room 391 1437 Bannock Street

TL;DR

The South Platte River Committee approved an increase to a construction contract with Mark Young Construction for the new Denver Parks and Recreation Northwest facility at Cuernavaca Park. The contract was increased by over $8.1 million and extended by 85 days to complete the office facility, maintenance building, and yard.

Key Decisions

  • Amendment to Mark Young Construction contract for DPR NW facility at Cuernavaca Park Passed
  • Contract value increase from $9,715,164.00 $8,131,024.00 added
  • Project completion deadline extension Extended 85 days to May 19, 2027
Agenda PDF

Agenda

  1. Consent Items
  2. 26-1176 Amends a contract with Mark Young Construction, LLC to add $8,131,024.00 for a new total of $9,715,164.00 and to add 85 days to the term for a new end date of 5-19-2027 to complete construction of a new office facility, maintenance building, and yard for the new DPR NW facility at Cuernavaca Park, in Council District 1 (DOTI-202581941/DOTI-202684929-01).
    Resolution